Question: Assume the network and data in the following Table A: ACTIVITY Immediate Predecessor (s) Time (weeks) A -- 3 B -- 4 C B 4

Assume the network and data in the following Table A:

ACTIVITY

Immediate Predecessor (s)

Time (weeks)

A

--

3

B

--

4

C

B

4

D

A

4

E

A, B

5

F

D, E

6

G

C, E

2

A. The duration for the project is _________ weeks (enter response as integer).

B. Assume the network and data in Table A: The duration for path B-C-G is _________ weeks (enter response as integer).

C. Assume the network and data in Table A: The slack for activity C is ________ week(s) (enter response as integer) .