Question: Assume the network and data in the following Table A: ACTIVITY Immediate Predecessor (s) Time (weeks) A -- 3 B -- 4 C B 4
Assume the network and data in the following Table A:
| ACTIVITY | Immediate Predecessor (s) | Time (weeks) |
| A | -- | 3 |
| B | -- | 4 |
| C | B | 4 |
| D | A | 4 |
| E | A, B | 5 |
| F | D, E | 6 |
| G | C, E | 2 |
A. The duration for the project is _________ weeks (enter response as integer).
B. Assume the network and data in Table A: The duration for path B-C-G is _________ weeks (enter response as integer).
C. Assume the network and data in Table A: The slack for activity C is ________ week(s) (enter response as integer) .