Question: Activity Immediate Predecessor Activity Time a -- 3 b -- 4 c a 4 d a 6 e b 5 f c,d 4 g e,f

Activity Immediate Predecessor Activity Time

a -- 3

b -- 4

c a 4

d a 6

e b 5

f c,d 4

g e,f 7

What is the latest time for Activity F?

What is the possible time that Activity E can be started without delaying the completion of the projection?