Question: Activity Immediate Predecessor Activity Time a -- 3 b -- 4 c a 4 d a 6 e b 5 f c,d 4 g e,f
Activity Immediate Predecessor Activity Time
a -- 3
b -- 4
c a 4
d a 6
e b 5
f c,d 4
g e,f 7
What is the latest time for Activity F?
What is the possible time that Activity E can be started without delaying the completion of the projection?
Can someone assist me with these questions? Thank you!!