Question: Activity Immediate Predecessor Activity Time a -- 3 b -- 4 c a 4 d a 6 e b 5 f c,d 4 g e,f

Activity Immediate Predecessor Activity Time

a -- 3

b -- 4

c a 4

d a 6

e b 5

f c,d 4

g e,f 7

What is the latest time that activity B can finish without delaying any other activities?

0?

8?

9?

4?

What is the latest time that activity B can start without delaying the project?

0?

8?

4?

7?