Question: Activity Immediate Predecessor Duration A --- 2 B --- 5 C A 12 D A 6 E B, C 11 F B, C 8 G
| Activity | Immediate Predecessor | Duration |
| A | --- | 2 |
| B | --- | 5 |
| C | A | 12 |
| D | A | 6 |
| E | B, C | 11 |
| F | B, C | 8 |
| G | E | 6 |
| H | D, F | 10 |
| I | G, H | 3 |
- Draw the network diagram and calculate the Critical Path.
- Calculate the maximum number of activities that can be delayed for the project not to be delayed.
- Calculate the maximum number of activities that can be delayed for the project not to have additional critical activities?