Question: Activity Immediate Predecessor Duration (days) A --- 2 B --- 5 C A 12 D A 6 E B, C 11 F B, C 8

Activity

Immediate Predecessor

Duration (days)

A

---

2

B

---

5

C

A

12

D

A

6

E

B, C

11

F

B, C

8

G

E

6

H

D, F

10

I

G, H

3

Calculate the maximum number of activities that can be delayed for the project not to be delayed.

Calculate the maximum number of activities that can be delayed for the project not to have additional critical activities?