Question: Activity Immediate Predecessor Duration (days) A --- 2 B --- 5 C A 12 D A 6 E B, C 11 F B, C 8
| Activity | Immediate Predecessor | Duration (days) |
| A | --- | 2 |
| B | --- | 5 |
| C | A | 12 |
| D | A | 6 |
| E | B, C | 11 |
| F | B, C | 8 |
| G | E | 6 |
| H | D, F | 10 |
| I | G, H | 3 |
Calculate the maximum number of activities that can be delayed for the project not to be delayed.
Calculate the maximum number of activities that can be delayed for the project not to have additional critical activities?