Question: Activity Immediate Predecessor Duration (days) Resource A --- 2 Yellow B A 4 Gray C B 6 Orange D A 6 Gray E A 8
| Activity | Immediate Predecessor | Duration (days) | Resource |
| A | --- | 2 | Yellow |
| B | A | 4 | Gray |
| C | B | 6 | Orange |
| D | A | 6 | Gray |
| E | A | 8 | Blue |
| F | A | 8 | Green |
| G | C, D, E, F | 4 | Yellow |
- Which of the following shows the Critical Chain path of the project?
- A B C G
- A B C D G
- A C D G
- A B D G
- A B D E G
- None of the above
- Which of the following shows the final duration of the project based on the Critical Chain?
- 10 days
- 14 days
- 15 days
- 25 days
- 20 days
- None of the above
- Which of the following shows the how many buffers (feeding plus project buffers) are there in the final schedule after applying the critical chain?
- 2
- 3
- 4
- 1
- 0
- None of the above
- Which of the following shows the total duration of the buffers (feeding plus project buffers) after applying the critical chain??
- 5 days
- 6 days
- 7 days
- 8 days
- 10 days
- None of the above
- Which of the activities will have feeding buffers at the end of them in the final schedule after applying the critical chain?
- Activities C, E, and F.
- Activities A, E, and F.
- Activities A, B, D, and G.
- Activities B, and D.
- Activities D, E, and F.
- None of the above
- Which of the following shows the latest finish time of activity D in the final schedule after applying the critical chain?
- 10
- 12
- 16
- 8
- 9
- None of the above