Question: Activity Immediate Predecessor Duration (days) Resource A --- 2 Yellow B A 4 Gray C B 6 Orange D A 6 Gray E A 8

Activity

Immediate Predecessor

Duration (days)

Resource

A

---

2

Yellow

B

A

4

Gray

C

B

6

Orange

D

A

6

Gray

E

A

8

Blue

F

A

8

Green

G

C, D, E, F

4

Yellow

  1. Which of the following shows the Critical Chain path of the project?
  1. A B C G
  2. A B C D G
  3. A C D G
  4. A B D G
  5. A B D E G
  6. None of the above
  1. Which of the following shows the final duration of the project based on the Critical Chain?
  1. 10 days
  2. 14 days
  3. 15 days
  4. 25 days
  5. 20 days
  6. None of the above

  1. Which of the following shows the how many buffers (feeding plus project buffers) are there in the final schedule after applying the critical chain?
  1. 2
  2. 3
  3. 4
  4. 1
  5. 0
  6. None of the above

  1. Which of the following shows the total duration of the buffers (feeding plus project buffers) after applying the critical chain??
  1. 5 days
  2. 6 days
  3. 7 days
  4. 8 days
  5. 10 days
  6. None of the above

  1. Which of the activities will have feeding buffers at the end of them in the final schedule after applying the critical chain?
  1. Activities C, E, and F.
  2. Activities A, E, and F.
  3. Activities A, B, D, and G.
  4. Activities B, and D.
  5. Activities D, E, and F.
  6. None of the above

  1. Which of the following shows the latest finish time of activity D in the final schedule after applying the critical chain?
  1. 10
  2. 12
  3. 16
  4. 8
  5. 9
  6. None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!