Question: Activity Immediate Predecessor Duration Resource Start --- 0 --- A --- 4 Yellow B --- 6 Red C --- 8 Orange D A 6 Gray
| Activity | Immediate Predecessor | Duration | Resource |
| Start | --- | 0 | --- |
| A | --- | 4 | Yellow |
| B | --- | 6 | Red |
| C | --- | 8 | Orange |
| D | A | 6 | Gray |
| E | A, B | 8 | Orange |
| F | D, E | 6 | Blue |
| Finish | C, F | 0 | --- |
Calculate the Critical Chain.
(Note: if you end up having decimal numbers for the buffers, please round them up to next integer number.)