Question: ACTIVITY IMMEDIATE PREDECESSOR DURATION (Weeks) A - 9 B - 11 C A 7 D A 10 E B,C 1 F B,C 5 G D,E
| ACTIVITY | IMMEDIATE PREDECESSOR | DURATION (Weeks) |
| A | - | 9 |
| B | - | 11 |
| C | A | 7 |
| D | A | 10 |
| E | B,C | 1 |
| F | B,C | 5 |
| G | D,E | 6 |
| H | D,E | 3 |
| I | H | 1 |
| J | F,G | 2 |
| K | G,I | 8 |
Using the data above:
a) Draw the Pert Network
b) Determine the critical path & project completion time
c) Determine total slack (float) for each activity
d) What is the impact on the project completion if activity F is delayed by 10 weeks?
e) What is the impact if activity D is delayed 4 weeks and activity F delayed 8 weeks?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts