Question: ACTIVITY IMMEDIATE PREDECESSOR DURATION (Weeks) A - 9 B - 11 C A 7 D A 10 E B,C 1 F B,C 5 G D,E

ACTIVITY

IMMEDIATE PREDECESSOR

DURATION (Weeks)

A

-

9

B

-

11

C

A

7

D

A

10

E

B,C

1

F

B,C

5

G

D,E

6

H

D,E

3

I

H

1

J

F,G

2

K

G,I

8

Using the data above:

a) Draw the Pert Network

b) Determine the critical path & project completion time

c) Determine total slack (float) for each activity

d) What is the impact on the project completion if activity F is delayed by 10 weeks?

e) What is the impact if activity D is delayed 4 weeks and activity F delayed 8 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!