Question: Based on the following information on a project, draw an AON network diagram. What is the critical path and what is the project completion time?
Based on the following information on a project, draw an AON network diagram. What is the critical path and what is the project completion time? Also, find the slack time for all the activities.
Activity Immediate Predecessor Time (Weeks)
A - 2
B - 3
C A 2
D A, B 4
E C 4
F C 3
G D, E 5
H F, G 2