Question: Activity Immediate Predecessor Duration (weeks) No. of Programmers Needed A 3 2 B A 1 1 C A 2 2 D B,C 3 1 E

Activity Immediate Predecessor Duration (weeks)
Activity Immediate Predecessor Duration (weeks)
Activity Immediate Predecessor Duration (weeks) No. of Programmers Needed A 3 2 B A 1 1 C A 2 2 D B,C 3 1 E 5 2 F 4 4 1 G E 5 1 E,F H 4 1 1 D,G,H 2 - Enter all answers in integer format. 1. If the project is to be completed in the minimum time, how many programmers are needed to work in week 7? Your answer is: 2. If the project is to be completed in the minimum time, how many programmers are needed to work in week 9? Your answer is: 3. If there are only two programmers available to work on this project, what is the minimum time that the project can be completed? Level the use of programmers using the following priority rules for assignment of resource: 4. Earliest start time 5. Minimum duration 6. Minimum slack time Your answer is: Please re-enter your

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!