Question: Activity Immediate Predecessor Optimistic Most Likely Pessimistic Sigma Variance A - 2 3 4 0 . 3 3 3 0 . 1 1 1 B

Activity
Immediate
Predecessor
Optimistic
Most
Likely
Pessimistic
Sigma
Variance
A
-
2
3
4
0.333
0.111
B
-
2
5
8
1
1
C
A
1
2
9
1.33
1.78
D
A
5
5
5
0
0
E
B, C
6
7
8
0.333
0.111
F
B
14
14
14
0
0
G
D, E
1
5
9
1.333
1.78
H
G, F
1
4
8
1.67
1.362
What is the variance of the critical path?
a.4.364
b.5.222
c.2.362
d.5.144
e.1.362