Question: Activity Immediate Predecessor Optimistic (o) Most Likely (m) Pessimistic (p) Mean time using (O+4*m+p)/6 Variance using ((p-o)/6)^2 A --- 2 5 8 5 1 B

Activity

Immediate Predecessor

Optimistic (o)

Most Likely (m)

Pessimistic (p)

Mean time using

(O+4*m+p)/6

Variance using

((p-o)/6)^2

A

---

2

5

8

5

1

B

---

5

5

5

5

.00

C

---

3

4

11

5

1.78

D

A, B

2

4

6

4

.44

E

B

1

3

5

3

.44

F

C

6

8

10

8

.44

G

D, E

2

6

10

6

1.78

STD

1.79

What is the probability that the project will be completed between 3 days earlier and 3 days later than expected?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!