Question: Activity Immediate Predecessor Optimistic (o) Most Likely (m) Pessimistic (p) Mean time using (O+4*m+p)/6 Variance using ((p-o)/6)^2 A --- 2 5 8 5 1 B
| Activity | Immediate Predecessor | Optimistic (o) | Most Likely (m) | Pessimistic (p) | Mean time using (O+4*m+p)/6 | Variance using ((p-o)/6)^2 |
| A | --- | 2 | 5 | 8 | 5 | 1 |
| B | --- | 5 | 5 | 5 | 5 | .00 |
| C | --- | 3 | 4 | 11 | 5 | 1.78 |
| D | A, B | 2 | 4 | 6 | 4 | .44 |
| E | B | 1 | 3 | 5 | 3 | .44 |
| F | C | 6 | 8 | 10 | 8 | .44 |
| G | D, E | 2 | 6 | 10 | 6 | 1.78 |
|
|
|
|
|
| STD | 1.79 |
What is the probability that the project will be completed between 3 days earlier and 3 days later than expected?