Question: Activity Immediate Predecessor Optimistic (o) Most Likely (m) Pessimistic (p) A --- 2 5 8 B --- 5 5 5 C --- 3 4 11
| Activity | Immediate Predecessor | Optimistic (o) | Most Likely (m) | Pessimistic (p) |
| A | --- | 2 | 5 | 8 |
| B | --- | 5 | 5 | 5 |
| C | --- | 3 | 4 | 11 |
| D | A, B | 2 | 4 | 6 |
| E | B | 1 | 3 | 5 |
| F | C | 6 | 8 | 10 |
| G | D, E | 2 | 6 | 10 |
A) What is the probability that the project will be completed in more than 15 days?
B) What is the probability that the project will be completed at least 3 days earlier than expected?
C) What is the probability that the project will be completed no more than 3 days later than expected?
D) What is the probability that the project will be completed between 3 days earlier and 3 days later than expected?
E) What due date has about 50% chance of being met?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock