Question: Activity Immediate Predecessor Optimistic (o) Most Likely (m) Pessimistic (p) A --- 2 5 8 B --- 5 5 5 C --- 3 4 11

Activity

Immediate Predecessor

Optimistic (o)

Most Likely (m)

Pessimistic (p)

A

---

2

5

8

B

---

5

5

5

C

---

3

4

11

D

A, B

2

4

6

E

B

1

3

5

F

C

6

8

10

G

D, E

2

6

10

A) What is the probability that the project will be completed in more than 15 days?

B) What is the probability that the project will be completed at least 3 days earlier than expected?

C) What is the probability that the project will be completed no more than 3 days later than expected?

D) What is the probability that the project will be completed between 3 days earlier and 3 days later than expected?

E) What due date has about 50% chance of being met?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!