Question: Activity Immediate Predecessor Optimistic Time ( Hr . ) Most Likely Time ( Hr . ) Pessimistic Time ( Hr . ) A 3 4

Activity Immediate Predecessor Optimistic Time
(Hr.) Most Likely Time (Hr.) Pessimistic Time
(Hr.)
A 3411
B A 222
C A 339
D B 357
E B 555
F C 456
G E,F 123
H D 129
I G,H 3411