Question: Activity Immediate Predecessor ( s ) Duration ( Weeks ) Activity Duration Immediate Predecessor ( s ) ( Weeks ) 6 A 4 F B

Activity
Immediate Predecessor(s)
Duration (Weeks)
Activity
Duration
Immediate Predecessor(s)
(Weeks)
6
A
4
F
B
C
B
10
7
G
2
C
H
F
8
D
A
5
F, G
11
E
B
3
J
D, E
8
a) Draw a network diagram and find the critical path and project completion time.
b) Calculate float/ slack of the all activities.
c) If $1000 can be saved for each delayed day of activity H, then how much dollar can be saved keeping the project completion time unchanged?
d) Activity G needs a delayed time of two weeks and an extra time of five weeks. Is it possible by keeping the project completion time unchanged? Explain.
e) The PM wants to shorten the duration of the activity I from 11 weeks to 9 weeks. What is the impact of this change on project completion time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!