Question: ACTIVITY Immediate Predecessor Normal Duration ( wks ) Minimum Duration ( wks ) Crash Costs ( $ / wk ) A - - - 4
ACTIVITY
Immediate Predecessor
Normal
Duration wks
Minimum
Duration wks
Crash Costs
$wk
A
B
C
A B
D
C
E
C
F
C
G
D
H
E
I
F
J
H I
What is the slack time for Activity F and the late start for Activity H
Group of answer choices
weeks, weeks
weeks, weeks
weeks, weeks
weeks, weeks
None of the above are correct.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
