Question: ACTIVITY Immediate Predecessor Normal Duration ( wks ) Minimum Duration ( wks ) Crash Costs ( $ / wk ) A - - - 4

ACTIVITY
Immediate Predecessor
Normal
Duration (wks)
Minimum
Duration (wks)
Crash Costs
($/wk)
A
---
4
4
---
B
---
3
2
100
C
A, B
5
3
200
D
C
4
4
---
E
C
2
1
300
F
C
1
1
---
G
D
3
2
200
H
E
1
1
---
I
F
1
1
---
J
H, I
3
1
100
What is the slack time for Activity F and the late start for Activity H?
Group of answer choices
2 weeks, 11 weeks
1 weeks, 11 weeks
3 weeks, 10 weeks
2 weeks, 12 weeks
None of the above are correct.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!