Question: Activity Immediate Predecessor ( s ) Te VAR Slack A - 5 0 . 4 4 4 0 B - 2 0 . 1 1

Activity
Immediate Predecessor(s)
Te
VAR
Slack
A
-
5
0.444
0
B
-
2
0.111
4
C
-
3
0.444
6.5
D
A
7.5
0.25
0
E
B
6.5
0.694
4
F
C
8
0.111
6.5
G
D, E
5
0.111
0
crithcal path is