Question: Activity Immediate Predecessor(s) Te VAR Slack A - 5 0.444 0 B - 2 0.111 4 C - 3 0.444 6.5 D A 7.5 0.25
Activity Immediate Predecessor(s) Te VAR Slack A - 5 0.444 0 B - 2 0.111 4 C - 3 0.444 6.5 D A 7.5 0.25 0 E B 6.5 0.694 4 F C 8 0.111 6.5 G D, E 5 0.111 0 What is the critical path for the project described by this table? Part 2 A. A-B-C B. B-E-G C. C-F D. A-D-G
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
