Question: Activity Optimistic Most Likely Pessimistic predecessor A 2 4 8 - B 2 2 2 - C 1 5 7 A D 4 5 6
| Activity | Optimistic | Most Likely | Pessimistic | predecessor |
| A | 2 | 4 | 8 | - |
| B | 2 | 2 | 2 | - |
| C | 1 | 5 | 7 | A |
| D | 4 | 5 | 6 | A |
| E | 3 | 5 | 9 | C,B |
| F | 1 | 0 | 5 | C, B |
| G | 2 | 7 | 9 | C, B |
- Calculate the Expected values for all activates, variances, and the slack (float)
- The Critical Path and the Expected completion time (TE)
| Activity | a | m | b | TE | Variance | Slack (float) |
| A | 2 | 4 | 8 | |||
| B | 2 | 2 | 2 | |||
| C | 1 | 5 | 7 | |||
| D | 4 | 5 | 6 | |||
| E | 3 | 5 | 9 | |||
| F | 1 | 0 | 5 | |||
| G | 2 | 7 | 9 |
CRITIAL PATH