Question: Activity Immediate Predecessor ( s ) Time ( days ) A minus 7 7 B A 4 4 C A 6 6 D B 6
Activity
Immediate Predecessors
Timedays
A
minus
B
A
C
A
D
B
E
B
F
C
G
D
H
E F
Part
Carls team should be able to complete the project in days.
Part
Critical path activities for Carl's project are