Question: Activity Immediate Predecessor ( s ) Time ( days ) A minus 3 B A 4 C A 6 D B 6 E B 4

Activity
Immediate Predecessor(s)
Time(days)
A
minus
3
B
A
4
C
A
6
D
B
6
E
B
4
F
C
4
G
D
6
H
E, F
8