Question: Activity Immediate Predecessor ( s ) Time ( days ) A minus 2 B minus 5 C minus 2 D B 1 0 E A
Activity
Immediate Predecessors
Timedays
A
minus
B
minus
C
minus
D
B
E
A D
F
C
G
E F
This exercise contains only parts b c and d
Part
b The critical activities for the leadership training program development project are
B D E G