Question: Activity Immediate Predecessor Time in Days A None 5 B A 2 . 7 D B and C 6 E 15 F B 9 G

Activity Immediate Predecessor Time in Days A

Activity Immediate Predecessor Time in Days A None 5 B A 2 . 7 D B and C 6 E 15 F B 9 G 4 H D, E, F, G 10 The above table is a simple project listing 8 activities and their respective time estimates: Using CPM, What is the slack for activity D?3 Select one: a. 23 Ob. 18 O c. 12 O d. None of the choices are correct O e. 9