Question: No explanation needed just quick answer please Activity Immediate Predecessor Time in Days A None 5 B 2 A 7 D B and C 6

No explanation needed just quick answer pleaseNo explanation needed just quick answer please

Activity Immediate Predecessor Time in Days A None 5 B 2 A 7 D B and C 6 E C 15 F B 9 G A 4 H D, E, F, G 10 The above table is a simple project listing 8 activities and their respective time estimates: Using the Single Time Estimate CPM procedure, what is the Late Finish Time for the activity F in this project? Select one: a. 16 days b. 27 days O c. None of the choices are correct O d. 18 days e. 10 days