Question: Activity Immediate Predecessor Time in Days A None 5 B 2 A 7 D Band C 6 E 15 F B 9 G A 30

Activity Immediate Predecessor Time in Days A
Activity Immediate Predecessor Time in Days A None 5 B 2 A 7 D Band C 6 E 15 F B 9 G A 30 H D, E, F, G 10 The above table is a simple project listing 8 activities and their respective time estimates: Using the Single Time Estimate CPM procedure, what is the Late Finish Time for the activity F in this project? Select one: a. 27 days b. 18 days C. None of the choices are correct o d. 10 days e 35 days