Question: Activity Immediate Predecessor Time (Week) A - 6 B A 3 C A 7 D C 2 E B, D 4 F D 3 G

Activity Immediate Predecessor Time (Week) A - 6 B A 3 C A 7 D C 2 E B, D 4 F D 3 G E, F 1. Draw the network diagram 2. What is Critical Path? 3. How many weeks will it take to complete the project? 4. How much slack does activity B have