Question: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 5 B A 4 C A 6 D A 6 E B 1 F C D 5
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D A
E B
F C D
G D F
H D
I E G H
b What is the critical path?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock