Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 6 D B 1 E C, D

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 4
C A 6
D B 1
E C, D 4
F D 3
G F 1
H E,G 2

b. What is the critical path?

  • A-C-E-F-G-H

  • A-B-D-E-H

  • A-B-D-F-G-H

  • A-C-E-H

c. How many weeks will it take to complete the project?

d. Which activities have slack, and how much?

multiple choice 2

  • B 1 week D 1 week F 1 week G 1 week.
  • B 5 weeks C 2 weeks F 3 weeks H 2 weeks.
  • B , 1 week C 2 weeks E 3 weeks H 4 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!