Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 6 D B 1 E C, D
Schedule the following activities using CPM:
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 3 | |
| B | A | 4 |
| C | A | 6 |
| D | B | 1 |
| E | C, D | 4 |
| F | D | 3 |
| G | F | 1 |
| H | E,G | 2 |
b. What is the critical path?
-
A-C-E-F-G-H
-
A-B-D-E-H
-
A-B-D-F-G-H
-
A-C-E-H
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
multiple choice 2
- B 1 week D 1 week F 1 week G 1 week.
- B 5 weeks C 2 weeks F 3 weeks H 2 weeks.
- B , 1 week C 2 weeks E 3 weeks H 4 weeks.