Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 6 D B 1 E C D

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 4
C A 6
D B 1
E C

D
4
F D 3
G F 1
H E

G
2

b. What is the critical path?

multiple choice 1

  • A-C-E-H

  • A-C-E-F-G-H

  • A-B-D-F-G-H

  • A-B-D-E-H

c. How many weeks will it take to complete the project?

Schedule the following activities using CPM:

d. Which activities have slack, and how much? OB. 1 week: C. 2 weeks; E. 3 weeksi H. 4 weeks. B. 5 weeks ; C. 2 weeks ;F. 3 weeksi H. 2 weeks. B. 1 week :D. 1 week ;F1 week : G . 1 week