Question: ACTIVITY IMMEDIATE PREDECESSORS a mb A 2 3 10 B 6 7 14 -- 4 7 10 D B,C 3 4 17 E A 5

ACTIVITY IMMEDIATE PREDECESSORS a mb A 2 3 10 B 6

ACTIVITY IMMEDIATE PREDECESSORS a mb A 2 3 10 B 6 7 14 -- 4 7 10 D B,C 3 4 17 E A 5 6 7 F D 7 8 15 G F,E 10 11 18 H G 4 5 18 a) Draw the network diagram of this project with both forward and backward calculations (ES, EF, LS,LF) and find the project completion time and slacks of the activities. b) What is the critical path of this project? c) Calculate the project variance. d) What is the probability of completing the project within 44, 40, and 38 weeks? ****** Z(1.4)=0.92, Z(-0.99)=0.16, Z(0.11)=0.54, Z(0.50)=0.69, Z(0.81)=0.79, Z(-0.50)=0.31