Question: Activity Immediate Predecessor(s) Duration (days) A ---- 5 B A 2 C A 4 D C,B 1 E C,B 6 F B 2 G D,E
| Activity | Immediate Predecessor(s) | Duration (days) |
| A | ---- | 5 |
| B | A | 2 |
| C | A | 4 |
| D | C,B | 1 |
| E | C,B | 6 |
| F | B | 2 |
| G | D,E | 3 |
| H | F,G | 4 |
1) Based on the above table, draw an ****AOA**** network.
2) List ALL paths and identify the critical path(s).
******Please make sure it is in the SAME format as the image I have attached--Activities on arrows not inside the bubble, like the image..*****
***THIS IS AN "ACTIVITY ON ARROW" (AOA) NETWORK. PLEASE DO NOT DRAW AN "ACTIVITY ON NODE" (AON) NETWORK*** THANK YOU!!!!