Question: Activity Immediate Predecessor Estimated Time ( days ) A 1 5 B A 1 2 C B 6 D B 5 E C 3 F

Activity Immediate
Predecessor Estimated Time (days)
A 15
B A 12
C B 6
D B 5
E C 3
F 8
G F 8
H F 9
I G 7
J H 14
K J 6
End D, E, I, K