Question: Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time a none 4 6 7 b a 1 2 3 c a 5 5 5

Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time
a none 4 6 7
b a 1 2 3
c a 5 5 5
d b 7 9 12
e b 2 4 8
f c, d 6 9 10

1. What is the standard deviation of the critical path?

2. what is the expected duration of the critical path?

3. What is the probability that the project will take longer than 28 weeks to complete?

4. What is the expected duration of Activity A?

5. What is the expected variance of Activity A?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!