Question: Activity Immediate Predecessors Time (weeks) a -- 8 b a 16 c a 12 d a 7 e b,c 22 f c,d 40 g e,f
| Activity | Immediate Predecessors | Time (weeks) |
| a | -- | 8 |
| b | a | 16 |
| c | a | 12 |
| d | a | 7 |
| e | b,c | 22 |
| f | c,d | 40 |
| g | e,f | 15 |
| h | -- | 14 |
| i | h | 9 |
| j | i | 13 |
| k | i | 7 |
| l | j | 36 |
| m | k | 40 |
| n | l,m | 9 |
| o | g,n | 10 |
1. Draw a precedence diagram. Use + to find ES, EF, LS, and LF. 2. Find activity slack for each activity: 3. Find Critical Path: CP =