Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 1 B A 4 C A 3 D B 2 E C, D
Schedule the following activities using CPM:
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 1 | |
| B | A | 4 |
| C | A | 3 |
| D | B | 2 |
| E | C, D | 5 |
| F | D | 2 |
| G | F | 2 |
| H | E, G | 3 |
b. What is the critical path?
| A-B-D-F-G-H | |
| A-C-D-F-G | |
| A-C-E-H | |
| A-B-D-E-H |
c. How many weeks will it take to complete the project?
Number of weeks
d. Which activities have slack, and how much?
| D, 2 weeks; G, 1 week; and H, 1 week. | |
| C, 3 weeks; F, 1 week; and G, 1 week. | |
| B, 3 weeks; D, 1 week; and E, 1 week. |