Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 1 B A 4 C A 3 D B 2 E C, D

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 1
B A 4
C A 3
D B 2
E C, D 5
F D 2
G F 2
H E, G 3

b. What is the critical path?

A-B-D-F-G-H
A-C-D-F-G
A-C-E-H
A-B-D-E-H

c. How many weeks will it take to complete the project?

Number of weeks

d. Which activities have slack, and how much?

D, 2 weeks; G, 1 week; and H, 1 week.
C, 3 weeks; F, 1 week; and G, 1 week.
B, 3 weeks; D, 1 week; and E, 1 week.