Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 5 C A 4 D B 2 E C D
| Schedule the following activities using CPM: |
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A |
| 3 |
| B | A | 5 |
| C | A | 4 |
| D | B | 2 |
| E | C D | 3 |
| F | D | 1 |
| G | F | 1 |
| H | E G | 4 |
| b. | What is the critical path? | ||||||||
|
|
| ||||||||
|
|
|
| c. | How many weeks will it take to complete the project? |
| Number of weeks |
|
| d. | Which activities have slack, and how much? | ||||||
|
|
| ||||||
|
|
|