Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 5 C A 4 D B 2 E C D

Schedule the following activities using CPM:

ACTIVITY

IMMEDIATE PREDECESSOR

TIME (WEEKS)

A

3

B

A

5

C

A

4

D

B

2

E

C D

3

F

D

1

G

F

1

H

E G

4

b.

What is the critical path?

A-C-E-H

A-C-E-F-G-H

A-B-D-F-G-H

A-B-D-E-H

c.

How many weeks will it take to complete the project?

Number of weeks

d.

Which activities have slack, and how much?

C 3 weeks F 1 week G 1 week.

B 3 weeks D 2 weeks E 4 weeks.

A 1 week B 2 weeks D 4 weeks.