Question: Activity Immediate Processor Optimistic A Most likely Time M Pessimistic time B A _____ 2 3 4 B ______ 2 4 6 C A 1
| Activity | Immediate Processor | Optimistic A | Most likely Time M | Pessimistic time B |
| A | _____ | 2 | 3 | 4 |
| B | ______ | 2 | 4 | 6 |
| C | A | 1 | 2 | 3 |
| D | B | 4 | 6 | 9 |
| E | C,D | 7 | 8 | 9 |
| F | D | 4 | 7 | 10 |
| G | E | 3 | 4 | 6 |
| H | E,F | 7 | 9 | 12 |
|
|
|
|
|
|
Construct the project network.
Determine the expected times and variances for the activities.
Determine the critical path after you have found ES, EF, LS, LF and slack. State the path and time expected to be taken.
What is the probability that the project would be completed within 28 weeks?
What time should be allowed such that there is a 95% chance of completion within that time?