Question: Activity Immediate Time Predecessor(s) (days) A 5 B 7 A 2 D A 3 E B 5 F 11 G 8 H DE 9 I

Activity Immediate Time Predecessor(s) (days) A 5
Activity Immediate Time Predecessor(s) (days) A 5
Activity Immediate Time Predecessor(s) (days) A 5 B 7 A 2 D A 3 E B 5 F 11 G 8 H DE 9 I F, G, H 3 Answer questions 1 to 3 using the following information: The following table represents Medro & Mariana's activities for their project to serve at home occasions. Draw the network diagram and answer the following questions: The latest finishing time for activity (Al is: (8 Points) a. 5 days b. 8 days c. 3 days d. none of the above 2 The earliest starting time for activity (H] is: (8 Points) a. on day 12 b on day 9 con day 8 d. none of the above 3 The slack for activity (D) is: (8 Points) a. 3 days b. 5 days c. 4 days d. none of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!