Question: Activity IPA Duration (days) A 4 B 4 C A 2 D B 8 E B 7. F A.C.D 8 G DE H G 4

Activity IPA Duration (days) A 4 B 4 C A 2 D B 8
Activity IPA Duration (days) A 4 B 4 C A 2 D B 8 E B 7. F A.C.D 8 G DE H G 4 1. Draw the project network (AON). 2. Compute the ES, EF, LS, and LF for each activity. 3. Compute the slack for each activity. 4. Find the critical path and the project duration