Question: Activity Min duration Most likely Max duration Predecessors A Requirements analysis 2 months 3 months 4 months None B Programming 6 months 7 months 9

Activity

Min duration

Most likely

Max duration

Predecessors

A Requirements analysis

2 months

3 months

4 months

None

B Programming

6 months

7 months

9 months

A

C Hardware acquisition

3 months

3 months

3 months

A

D Train users

12 months

12 months

12 months

A

E Implementation

3 months

5 months

7 months

B, C

F Testing

1 month

1 month

2 months

E

Conduct a PERT analysis and identify expected completion time for each activity.

Calculate the probability of completing the project in the following periods:

18 months, 17 months, 16 months, 15 months

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!