Question: Activity Min duration Most likely Max duration Predecessors A Requirements analysis 2 months 3 months 4 months None B Programming 6 months 7 months 9
Activity | Min duration | Most likely | Max duration | Predecessors |
A Requirements analysis | 2 months | 3 months | 4 months | None |
B Programming | 6 months | 7 months | 9 months | A |
C Hardware acquisition | 3 months | 3 months | 3 months | A |
D Train users | 12 months | 12 months | 12 months | A |
E Implementation | 3 months | 5 months | 7 months | B, C |
F Testing | 1 month | 1 month | 2 months | E |
Conduct a PERT analysis and identify expected completion time for each activity.
Calculate the probability of completing the project in the following periods:
18 months, 17 months, 16 months, 15 months
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
