Question: Activity Minimum Most Likely Maximum a m b A 4 1 5 0 5 9 B 5 4 6 0 6 6 C 5 8

Activity
Minimum
Most Likely
Maximum
a
m
b
A
41
50
59
B
54
60
66
C
58
70
82
D
32
41
44
What is the estimated expected (mean) time for activity D?
Group of answer choices
40 days
32 days
38
42 days
45 day