Question: Start End B Time estimates (days) Activity Minimum Most Likely Maximum a m b A 41 50 59 B 54 60 66 C 58 70

Start End B Time estimates (days) Activity
Start End B Time estimates (days) Activity
Start End B Time estimates (days) Activity
Start End B Time estimates (days) Activity
Start End B Time estimates (days) Activity Minimum Most Likely Maximum a m b A 41 50 59 B 54 60 66 C 58 70 82 D 32 41 44 What is the estimated expected (mean) time for activity D? What is the estimated variance in the time for activity D? O 4 days O O days O 9 days O 16 days O 33 days What is the estimated expected (mean) time for project completion? 100 days O 41 days 221 days 120 days O 70 days Question 16 What is the estimated standard deviation of the expected time for the critical path? 5 days 8 days 25 days What is the probability that this project will be completed after 130 days? O 0.9772 O 0.0228 O 0.1587 O 0.8413 O 0.0456

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!