Question: Activity name. Duration predecessors A - 7 - none B - 3 - a C - 8 - a D - 2 - b ,

Activity name. Duration predecessors
A-7-none
B-3-a
C-8-a
D-2-b,c
E-5-d
A.activity C can be delayed by one day without delaying the overall project
b. the latest activity D can start without delaying the project is on day 15
C. float for activity D is equal to 0 therefore it is not an activity along the projects critical path
D. activity a is on the critical path which means late finish equals early start