Question: Activity name. Duration predecessors A - 7 - none B - 3 - a C - 8 - a D - 2 - b ,
Activity name. Duration predecessors
Anone
Ba
Ca
Dbc
Ed
Aactivity C can be delayed by one day without delaying the overall project
b the latest activity D can start without delaying the project is on day
C float for activity D is equal to therefore it is not an activity along the projects critical path
D activity a is on the critical path which means late finish equals early start