Question: Given the following information regarding a project: Activity Duration Predecessors a 2 None b 3 None c 2 a d 4 a , b e
Given the following information regarding a project:
Activity
Duration
Predecessors
a
None
b
None
c
a
d
a b
e
c
f
c
g
d e
h
f g
Which of the following is NOT a path in the network?
Answer
acfh
acegh
adgh
bdgh
bdeh
What is the critical path?
acfh
acegh
adgh
bdgh
bdeg
How long will it take to complete the project?
What is the LS for activity a
What is the LF for activity f
What is the EF for activity g
What is the LF for activity h
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
