Question: Given the following information regarding a project: Activity Duration Predecessors a 2 None b 3 None c 2 a d 4 a , b e

Given the following information regarding a project:
Activity
Duration
Predecessors
a
2
None
b
3
None
c
2
a
d
4
a, b
e
4
c
f
3
c
g
5
d, e
h
2
f, g
7. Which of the following is NOT a path in the network?
Answer
a-c-f-h
a-c-e-g-h
a-d-g-h
b-d-g-h
b-d-e-h
8. What is the critical path?
a-c-f-h
a-c-e-g-h
a-d-g-h
b-d-g-h
b-d-e-g
9. How long will it take to complete the project?
4
9
10
13
15
10. What is the LS for activity a?
0
1
3
4
5
11. What is the LF for activity f?
10
13
15
19
12. What is the EF for activity g?
7
8
10
13
15
13. What is the LF for activity h?
7
8
10
13
15

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!