Question: Activity name. Duration predecessors A - 7 - none B - 3 - a C - 8 - a D - 2 - b ,

Activity name. Duration predecessors A-7-none B-3-a C-8-a D-2-b,c E-5-d From this drawn network diagram, can you help me analyze which is the correct statement and explain why.A.activity C can be delayed by one day without delaying the overall project b. the latest activity D can start without delaying the project is on day 15 C. float for activity D is equal to 0 therefore it is not an activity along the projects critical path D. activity a is on the critical path which means late finish equals early start
 Activity name. Duration predecessors A-7-none B-3-a C-8-a D-2-b,c E-5-d From this