Question: Activity Normal Duration (weeks) Minimum Duration (weeks) Normal Cost ($) Maximum Cost ($) A 10 8 50,000 62,000 B 5 4 25,000 32,000 C 4

| Activity | Normal Duration (weeks) | Minimum Duration (weeks) | Normal Cost ($) | Maximum Cost ($) |
| A | 10 | 8 | 50,000 | 62,000 |
| B | 5 | 4 | 25,000 | 32,000 |
| C | 4 | 3 | 20,000 | 28,000 |
| D | 12 | 8 | 60,000 | 90,000 |
| E | 15 | 13 | 75,000 | 92,000 |
| F | 6 | 4 | 30,000 | 42,000 |
| G | 8 | 5 | 40,000 | 62,500 |
| H | 7 | 6 | 35,000 | 44,500 |
LP Formulation
Decision variables
FA = finish time of activity A
FB = finish time for activity B
FC = finish time for activity C
FD = finish time for activity D
FE = finish time for activity E
FF = finish time for activity F
FG = finish time for activity G
FH = finish time for activity H
SA = start time of activity A
SB = start time of activity B
SC = start time of activity C
SD = start time of activity D
SE = start time of activity E
SF = start time of activity F
SG = start time of activity G
SH = start time of activity H
E0 = event time of event 0 = project start time
E1 = event time of event 1
E2 = event time of event 2
E3 = event time of event 3
E4 = event time of event 4
E5 = event time of event 5
E6 = event time of event 6 = desired project completion time
TA = crash time of activity A
TB = crash time of activity B
TC = crash time of activity C
TD = crash time of activity D
TE = crash time of activity E
TF = crash time of activity F
TG = crash time of activity G
TH = crash time of activity H
Note: The crash time for an activity is the amount of time subtracted from the activitys normal duration
Parameters
DA = normal duration of activity A
DB = normal duration of activity B
DC = normal duration of activity C
DD = normal duration of activity D
DE = normal duration of activity E
DF = normal duration of activity F
DG = normal duration of activity G
DH = normal duration of activity H
Question 1
What is the shortest possible completion time (in weeks) for this project?
>= 20 and
>= 23 and
>= 26 and
> 29
Question 2
How much will this project cost (in $s) under normal conditions?
>= 300,000 and
>= 350,000 and
>= 400,000
Question 3
What would be the total cost of activity D if this activity is completed in 10 weeks?
>= 60,000 and
>= 70,000 and
>= 80,000
Question 4
What is the cheapest way to reduce the duration of the project by one week from its normal duration?
Reduce activity A by one week
Reduce activity B by one week
Reduce activity C by one week
Reduce activity D by one week
Reduce activity E by one week
Reduce activity F by one week
Reduce activity G by one week
Reduce activity H by one week
Question 5
Which of the following expressions is the objective for this crashing problem?
Minimize 6,000 DA + 7,000 DB + 8,000 DC + 7,500 DD + 8,500 DE + 6,000 DF + 7,500 DG + 9,500 DH
Minimize 62,000 TA + 32,000 TB + 28,000 TC + 90,000 TD + 92,000 TE + 42,000 TF + 62,500 TG + 44,500 TH
Minimize 6,000 FA + 7,000 FB + 8,000 FC + 7,500 FD + 8,500 FE + 6,000 FF + 7,500 FG + 9,500 FH
Minimize 6,000 TA + 7,000 TB + 8,000 TC + 7,500 TD + 8,500 TE + 6,000 TF + 7,500 TG + 9,500 TH
Question 6
Which of the following expressions would be included as a constraint in a linear programming formulation of the crashing problem for the project?
FB=SB-DB+TB
DE>=0
E3>=FD
TE>=2
4 B P I GStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
