Question: Activity Normal Preceding Crash Maximum Time Activity Cost Crash Time A 5 None 3 0 1 B 3 None 6 0 2 C 4 A
Activity Normal Preceding Crash Maximum
Time Activity Cost Crash Time
A None
B None
C A
D A
E B
F C
G D
H E
I F G H
Use the information provided to crash onetime unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. The project duration is time units and the total direct cost is $ Indirect costs for each project duration are $ time units $ time units $ time units $ time units and $ time units compute the total project cost for each duration. What is the optimal cost and time?