Question: Activity Normal Preceding Crash Maximum Time Activity Cost Crash Time A 2 None 0 0 B 3 A 1 0 0 1 C 5 A
Activity Normal Preceding Crash Maximum
Time Activity Cost Crash Time
A None
B A
C A
D B
E C
F C
G D E F
Use the information provided to crash onetime unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. The project duration is time units and the total direct cost is $ Assume the total indirect cost for the project is $ and there is a savings of $ per time unit reduced. Compute the total project cost for each duration. What is the optimal cost and time?
Group of answer choices
$ at time units
$ at time units
$ at time units
$ at time units