Question: Activity Normal Preceding Crash Maximum Time Activity Cost Crash Time A 1 0 None 8 0 2 B 8 None 3 0 3 C 5

Activity Normal Preceding Crash Maximum
Time Activity Cost Crash Time
A 10 None 802
B 8 None 303
C 5 None 401
D 11 A 502
E 15 C 1004
F 6 B,D,E 301
Use the information provided to crash one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. The project duration is 27 time units and the total direct cost is $300. Indirect costs for each duration are $300(27 days), $240(26 days), $180(25 days), $120(24 days), $60(23 days), and $50(22 days), compute the direct, indirect and total costs for each duration. The customer offers you $10 for every day you shorten the project from your original network. What is the optimum cost-time schedule (duration) with the incentive given?
Group of answer choices

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!