Question: Activity Normal Time Crash Time Normal Cost Crash Cost Immediate Predecessors Cost per crash A 3 2 1000 1600 - 600 B 2 1 2000

Activity

Normal Time

Crash Time

Normal Cost

Crash Cost

Immediate Predecessors

Cost per crash

A

3

2

1000

1600

-

600

B

2

1

2000

2700

-

700

C

11

1

300

500

-

20

D

7

3

1300

1600

A

75

E

6

3

850

1000

B

50

F

2

1

4000

5000

C

1000

G

4

2

1500

2000

D, E

250

a.) Crash this project to 10 weeks at the least cost

b.) Crash this project to seven weeks (which is the maximum it can be crashed) at the least cost

Show explanation please.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!