Question: Activity Normal Time Crash Time Normal Cost Crash Cost Immediate Predecessors Cost per crash A 3 2 1000 1600 - 600 B 2 1 2000
| Activity | Normal Time | Crash Time | Normal Cost | Crash Cost | Immediate Predecessors | Cost per crash |
| A | 3 | 2 | 1000 | 1600 | - | 600 |
| B | 2 | 1 | 2000 | 2700 | - | 700 |
| C | 11 | 1 | 300 | 500 | - | 20 |
| D | 7 | 3 | 1300 | 1600 | A | 75 |
| E | 6 | 3 | 850 | 1000 | B | 50 |
| F | 2 | 1 | 4000 | 5000 | C | 1000 |
| G | 4 | 2 | 1500 | 2000 | D, E | 250 |
a.) Crash this project to 10 weeks at the least cost
b.) Crash this project to seven weeks (which is the maximum it can be crashed) at the least cost
Show explanation please.